Compute the Work-in-Process transferred to the finished goods warehouse on April 30 using the following information:
 Work-In-Process Inventory, April 30 $175Direct material purchased during April 150Work-In-Process Inventory, April 1 200Direct labor costs incurred 300Manufacturing overhead costs 250Direct materials used in production 125\begin{array}{lrr} \text { Work-In-Process Inventory, April 30 } &\$175\\ \text {Direct material purchased during April } &150\\ \text {Work-In-Process Inventory, April 1 } &200\\ \text {Direct labor costs incurred } &300\\ \text {Manufacturing overhead costs } &250\\ \text {Direct materials used in production } &125\\\end{array}


A) $650.
B) $675.
C) $700.
D) $750.