Multiple Choice
Using the assembly-line balancing procedure, which of the following is the required cycle time if the production time in minutes per day is 1,440 and the required output per day in units is 2,000?
A) 0.72
B) 1.388
C) 250
D) 500
E) Cannot be determined from the information above