Solved

Brutus Construction
Brutus Construction Started Work on a New High

Question 128

Essay

Brutus Construction
Brutus Construction started work on a new high rise building on January 1, 2019, The project completion date is December 2021. The contract price is $54,000,000. The following are the actual costs incurred and estimates of cost to complete the project.
 Years  Actual costs incurred  Estimated costs to complete 2019$15,000,000$30,000,000202022,500,00022,500,000202117,500,000−0−\begin{array} { r c c } \text { Years } & \text { Actual costs incurred } & \text { Estimated costs to complete } \\2019 & \$ 15,000,000 & \$ 30,000,000 \\2020 & 22,500,000 & 22,500,000 \\2021 & 17,500,000 & - 0 -\end{array}
-Refer to Brutus Construction. Calculate gross profit or loss for 2019, 2020 and 2021 using the percentage of completion method.