Following are the three time estimates for a task in a project: optimistic completion time = 2 weeks
Most likely completion time = 4 weeks
Pessimistic completion time = 7 weeks
Compute the task variance.
A) 0.5 weeks
B) 1.23 weeks
C) 0.69 weeks
D) 2.25 weeks
Correct Answer:

Verified
Correct Answer:
Verified