Multiple Choice
A budgeting approach that requires a cost centre to plan its expenditure specifically around the programs or projects conducted by the cost centre is known as:
A) Discrete budgeting
B) Kaizen budgeting
C) Flexible budgeting
D) Program budgeting
Correct Answer:

Verified
Correct Answer: