Blocking between floor joists is required where


A) the joists bear on a beam.
B) the joists bear on a wall.
C) the joists are hung on a beam using joist hangers.
D) all of the above.
E) both A and B.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q38: The header over an opening in a

Q39: What is the minimum thickness of ridge

Q40: In a roof with a ridge beam,<br>A)ceiling

Q41: The type of WLF construction that has

Q42: WLF construction originated in<br>A)France.<br>B)the United Kingdom.<br>C)Norway.<br>D)Australia.<br>E)the United

Q44: A jack stud is always accompanied by

Q45: In referring to a floor or roof

Q46: In the building industry, the slope of

Q47: With the help of three- dimensional sketches,

Q48: The most commonly used contemporary construction for

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2026) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines