Multiple Choice
The primary purpose of full- depth blocking in a floor frame is to
A) prevent buckling of floor joists.
B) give additional nailing surface for a gypsum board ceiling.
C) give additional nailing surface for floor sheathing.
D) reduce compressive stresses in floor joists.
E) reduce tensile stresses in floor joists.
Correct Answer:

Verified
Correct Answer:
Verified
Q49: In platform- frame construction, the wall framing,
Q50: The standard spacings of framing members in
Q51: The top plate in a WLF wall
Q52: In a podium- type building, the horizontal
Q53: The shortening in the height of wood
Q55: If a ridge beam is used in
Q56: Explain what a floor framing plan is.
Q57: In platform- frame construction, the wall framing,
Q58: Describe various functions of wall sheathing in
Q59: A header over an opening bears directly