When a Project Is Completed on Time,the Project Team Must

Question 16

Multiple Choice

When a project is completed on time,the project team must accomplish all of the following activities EXCEPT:


A) use alternative dispute resolution
B) capture and share lessons learned
C) close active contracts
D) request customer acceptance of the deliverables

Correct Answer: