All of the following are benefits that can be attributed to the effective use of a risk management plan EXCEPT:
A) It enables project managers to eliminate, or reduce, the impact of some threats.
B) It enables the project manager to identify and eliminate all risks
C) It facilitates communication with project stakeholders.
D) It enables project managers to capitalize on some opportunities.