Multiple Choice
The milestone schedule in the project charter accomplishes all the following EXCEPT:
A) divides the project into many detailed activities to derive the milestones
B) lists major milestones and deliverables the project team needs to complete.
C) identifies planned completion dates for major milestones.
D) divides the project into a few (3 to 8) intermediate points whose completion can be verified.