There are several tasks that a project customer (or sponsor acting in that capacity) can do to enhance the probability of success. All of the following are generally performed jointly with the project contractor who will perform the work EXCEPT:
A) make honest decisions about contractor selection
B) develop clear requirements
C) use a control system
D) conduct a kick-off meeting
Correct Answer:

Verified