Project planning teams use project life cycle models because various types of projects have differing demands. Which of the following sequences of stages is most appropriate for a life cycle model for improvement projects?
A) define - measure - analyze - improve - control
B) concept definition - demonstration - development - production
C) pre-planning - design - procurement - construction - start up
D) concept - requirements - design - code - test - turnover