Multiple Choice
A project is resource leveled without resource-limited constraints and the project did not extend beyond its required completion after leveling.Which of the following must have been false?
A) The critical path of the project had negative slack.
B) Tasks using the same resources that were leveled were not on the critical path.
C) At least one of the activities using the resources that were leveled had positive slack.
D) The project had adequate positive slack in all the paths to accommodate the leveling.
Correct Answer:

Verified
Correct Answer:
Verified
Q15: If resources are to be considered in
Q16: Resources are not usually hired on a
Q17: In _, when several activities need the
Q18: _ is a method for developing the
Q19: Resource constraints are represented in the network
Q21: Resource leveling, or smoothing, is a method
Q22: Resource-limited scheduling attempts a schedule in which
Q23: Resources in a project are<br>A) human resources
Q24: Activities in a network diagram are drawn
Q25: This example has level resources of three