  5. Question
    In PERT Analysis, the Probability of the Optimistic Time Occurring
Solved

In PERT Analysis, the Probability of the Optimistic Time Occurring

Question 110

Question 110

Multiple Choice

In PERT analysis, the probability of the optimistic time occurring should be on the order of


A) 1/3.
B) 1/6.
C) 1/10.
D) 1/100.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q105: PERT and CPM are quantitative analysis tools

Q106: Table 11-1<br>The following represents a project with

Q107: Table 11-7<br>A project manager calculated early and

Q108: The two common techniques for drawing PERT

Q109: Activity B of a project has a

Q111: Table 11-8<br>A mad scientist has identified the

Q112: In a PERT network, the latest (activity)start

Q113: PERT assumes that the total completion time

Q114: One PERT/COST assumption is that money is

Q115: Your company is considering submitting a bid

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2026) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines