Multiple Choice
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 15 days, respectively, compute the PERT standard deviation for this activity.
A) 2
B) 4
C) 5
D) 15
Correct Answer:

Verified
Correct Answer:
Verified