Which of the Following Statistics from Studies on Failed Projects

Question 83

Multiple Choice

Which of the following statistics from studies on failed projects is not true?


A) Large software projects on average run 33 percent over schedule.
B) Large software projects on average run 66 percent over budget.
C) Between 30 and 40 percent of all software projects are "runaway" projects that far exceed the original schedule and budget projections and fail to perform as originally specified.
D) As many as 17 percent of projects turn out so badly that they can threaten the existence of the company.
E) The average cost overrun of IT projects is 20 percent.

Correct Answer: